JANUARY 2021

Land Clearance Completed

JANUARY 2021
FEBRUARY 2021

Groundbreaking Day at Tower 33

FEBRUARY 2021
March 2021

Borepiling Commence

March 2021
April 2021

Borepiling Continues with PDA Testing

April 2021
May 2021

Site Advertisement Hoarding has finally been installed!!!!

May 2021
June 2021

Borepiling is halted due to MCO guidelines

June 2021
July 2021

Borepiling Works Continues

July 2021
August 2021

Borepiling Works still in progress

August 2021
September 2021

Electric Pole and Wiring is removed

September 2021
January 2024

Tower 33 is Higher then Cityone Megamall

January 2024